Dear all,
first, I want to thank the partners that have already contacted me and have
sent me all the information I requested. Following your replies (to my
email from 30.01.19) I would like to update you on our status today.
*Financial information*
We would like to invite FSFE and OFE to send us an invoice of 20% (for the
third payment which is due now) on the FOSS4SMEs project.
We would like to invite DIT to send us an invoice of 80% (for the first,
second and third payment together) on the FOSS4SMEs project.
*Timesheets *(scanned as "Certified copies", signed and stamped)
We would like FSFE, OFE and DIT to send us the timesheets for Oct, Nov and
Dec 2018 asap (per person, per staff category, per output AND Only integer
numbers at the sum).
*Travel Documents*
We would like FSFE, OFE and DIT to send us the following documents for
every person for the Dublin trip (scanned as "Certified copies", signed and
stamped)
- Flight itinerary and boarding passes
- Travel invoices, receipts (plane, bus, etc.)
- Subsistence costs invoices/ receipts (hotel, etc.)
*Certificates of participation – Dublin Meet.*
We would like FSFE and DIT to scan and upload the certificates as PDF files
in the folder --> K:\team\foss4smes\5. Meetings\3. Dublin
Meeting\Certificate of Participation
I checked with our financial department and this is how we need them. The
.jpg files will not do.
*Participants list*
We are waiting for OFE to send us per post the list that everyone has
signed.
*Minutes*
I have reviewed the minutes on 12.02.19. DIT and FSFE are now finalising
the document. Please send it to us/me within this week.
*Keybase*
The documents still remaining in our Google Drive folder are not valid
anymore. From now on, we are only using Keybase.
*O2/A1 Updates of Units after 1st Peer Review from OFE and FSFE *
We would like FSFE and OFE to update us on the status of the files they
received from the partners. Since my last communication with you, Unit 2.3,
2.4, 3 and 5 were missing from Keybase. As a result the 2nd review is still
not conducted and so the import of the units in Moodle cannot start
tomorrow as planned. We need to discuss a new timeline and see how we can
deal with this new delay.
Concerning Unit 1, I have sent (Max and Sivan) an e-mail on 30.01.19
(topic: O2/A1 1st Peer Review - results and guidelines ) with my thoughts
and questions on the issues I had in Unit 1. Please try to get back to me
on these points within your next review.
*FOSS tool for Video hosting*
We would like FSFE to inform us on the alternative FOSS tool for hosting
videos.
*2nd Newsletter*
We would like DIT, DLEARN, FSFE and OFE to prepare their text and upload it
in the file located --> K:\team\foss4smes\1. Management\Newsletters
*Test Plan*
Dear Brian, I would like to receive your example test plan on website
testing and then I will prepare our own.
Thank you all in advance for getting back to me, if possible before our
telco (tommorow).
There are a lot of things to discuss and I am looking forward to hear from
you. Let me know if you want to add sth in our discussion points.
Best,
Katerina
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>
Dear Max and Sivan,
from what I can see in the Keybase folder "K:\team\foss4smes\2.
Implementation\Outputs\Output 2\A1 Training course contents", we miss
updated versions of Units 2.3, 2.4., 3 and 5. I couldn't find files/updates
from these partners. Have you received them personally?
I summarise here the status for the Content Development, but please feel
free to adjust it, and add the dates of other files in case you have them.
O2/A1 Partners 1st submission Update after Review from SKUNI Update after
proofreading from DIT Updates after 1st Peer Review of OFE and FSFE Updates
after 2nd peer review (by 15.02.19)
ATL - Unit 1 29.11. 13.12.18 09.01.19 03.02.19
OFE - Unit 2.1
and 2.2. 03.12. 12.12.18 08.01.19 30.01.19
Dlearn - Unti 2.3
and 2.4. 14.09. 14.12.18 (12:04h) 14.12.18 (19:14)
Dit - Unit 3 12.12. - 09.01.19
Skovde - Unit 4 30.11. - 17.12.18 06.02.19
FSFE - Unit 5 08.01.19 -
-
How do we want to proceed now? Should we wait until you have all the units,
so that you can review them as a whole? Or have you already started working
on them to provide us with your feedback?
Let me know when we can discuss this further in order to adjust our strict
timeplan.
Best,
Katerina
Στις Τρί, 12 Φεβ 2019 στις 10:09 π.μ., ο/η Sivan Pätsch <
sivan(a)openforumeurope.org> έγραψε:
> Good morning Katerina,
>
> I could also find in the below folder units 2.1-2.2 (30 Jan) and unit 4 (5
> Feb). Max, I think you said that unit 2.3-2.4 and unit 5 were also updated.
> Are they on the keybase?
>
> That would mean that only unit 3 from DIT is missing. If this is the case,
> Katerina, could you ping them again and ask when they intent do deliver the
> edited version?
>
> Best,
> Sivan
>
> team/foss4smes/2. Implementation/Outputs/Output 2/A1 Training course
> contents/Peer Review - 1st round/After Peer Review
>
> On Tue, 2019-02-12 at 09:32 +0200, Katerina Tsinari wrote:
>
> Dear Max and Sivan,
>
> from what I can see in the Keybase folder "K:\team\foss4smes\2.
> Implementation\Outputs\Output 2\A1 Training course contents", we only have
> an updated version of Unit 1. I couldn't find files/updates from the other
> partners. Have you received them personally?
>
> I summarised the status for the Content Development in this old table, but
> please feel free to adjust it, and add the dates of other files in case you
> have them:
>
> O2/A1 Partners 1st submission Update after Review from SKUNI Update after
> proofreading from DIT Updates after 1st Peer Review of OFE and FSFE Updates
> after 2nd peer review (by 15.02.19)
> ATL - Unit 1 29.11. 13.12.18 09.01.19 03.02.19
> OFE - Unit 2.1
> and 2.2. 03.12. 12.12.18 08.01.19
> Dlearn - Unti 2.3
> and 2.4. 14.09. 14.12.18 (12:04h) 14.12.18 (19:14)
> Dit - Unit 3 12.12. - 09.01.19
>
> Skovde - Unit 4 30.11. - 17.12.18
> FSFE - Unit 5 08.01.19 -
> -
>
> How do we want to proceed now? Should we wait until you have all the
> units, so that you can review them as a whole?
> Let me know if we need to discuss this further in order to adjust our
> strict timeplan.
>
> Thank you for your support.
>
> Best,
> Katerina
>
> Στις Κυρ, 10 Φεβ 2019 στις 7:45 μ.μ., ο/η Max Mehl <max.mehl(a)fsfe.org>
> έγραψε:
>
> Dear all,
>
> From what I can see in this email thread and Keybase, we meanwhile have
> updated versions for all Units except Unit 3. Could you please let Sivan
> and me know when you would be able to send us a new version?
>
> Thanks!
>
> Best,
> Max
>
>
> ~ Max Mehl [2019-01-21 13:02 +0100]:
> > Dear all,
> >
> > As presented in Dublin, Sivan and I have finished the first round of
> peer reviews. Attached and in Keybase [^1] you will find the results with
> comments and in-text changes in the folders of OFE and FSFE.
> >
> > Attached and in Keybase you will also find a document with recommended
> style guidelines which summarise issues and inconsistencies we've found in
> most documents. Please read and consider implementing them while editing
> your learning units.
> >
> > Please note that all peer-reviewed documents are in the ODT format.
> Please consider using LibreOffice when editing the files to guarantee best
> compatibility amongst all partners.
> >
> > Timeline for the next steps related to O2/A1 looks like the following:
> >
> > - 03.02.: all partners updated their units based on peer review and
> guidelines
> > - 08.02.: 2nd round of peer review finished
> > - 19.02.: all partners implement feedback from 2nd peer review
> > - 01.03.: raw import of all units finished
> >
> > Thanks for your work! If you have any questions regarding both FSFE's
> > and OFE's comments, please do not hesitate to ask us.
> >
> > Best,
> > Max
> >
> >
> > [^1]: 2. Implementation -> Outputs -> Output 2 -> A1 Training course
> > contents -> Peer Review - 1st round
>
> --
> Max Mehl - Programme Manager - Free Software Foundation Europe
> Contact and information: https://fsfe.org/about/mehl | @mxmehl
> Become a supporter of software freedom: https://fsfe.org/join
> _______________________________________________
> Foss4smes-team mailing list
> Foss4smes-team(a)lists.fsfe.org
> https://lists.fsfe.org/mailman/listinfo/foss4smes-team
>
> This mailing list is covered by the FSFE's Code of Conduct. All
> participants are kindly asked to be excellent to each other:
> https://fsfe.org/about/codeofconduct
>
>
>
> --
> *Sivan Pätsch*
> Digital Policy Adviser
> OpenForum Europe
> tel +32 (0) 2 486 4151
> mob +32 (0) 484 90 71 23
> web http://www.openforumeurope.org
> Follow us on Twitter @OpenForumEurope
> <https://twitter.com/OpenForumEurope>
> --
> OFE Limited, a private company with liability limited by guarantee
> Registered in England and Wales with number 05493935
> Registered office: Claremont House, 1 Blunt Road, South Croydon, Surrey
> CR2 7PA, UK
> <https://maps.google.com/?q=1+Blunt+Road,+South+Croydon,+Surrey+CR2+7PA,+UK&…>
>
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>
Dear all,
Apologies for the multiple emailing, but just noticed the link I have
you has merged with the words used afterwards and the link gives an
error message. This is the actual link:
https://fsfe.org/campaigns/ilovefs/artwork/artwork.en.html
Apologies again
Cheers,
G
> On Mon, 11 Feb 2019 at 10:03, Galia Mancheva <galia(a)fsfe.org
> <mailto:galia@fsfe.org>> wrote:
>
> Dear FOSS4SMEs partners,
>
> I am contacting you with a communications related proposal.
> We, at FSFE,are having an annual campaign taking place on February
> 14th
> each year, where wepromote the use of FOSS.
>
> The way we have done it online so far is by placing the visuals of the
> slogan "I love Free Software"
> https://fsfe.org/campaigns/ilovefs/artworkeverywhere we can: websites,
> blogs, social media platforms (posting,reposting) on February 14th. As
> you would notice, the visuals do not include FSFE name, which makes it
> easier for other companies and organisations to participate and spread
> the message. Some of our volunteers are going to give a 15 minute talk
> in front of students with tech profiles on the benefits of using FS on
> that day.
>
> In the context of FOSS4SMEs, it makes sense that the project would
> promote the day, but we would like to ask if anyone of you would be
> willing to participate and share any of those visuals on the online
> platforms you are using or on the FOSS4SMEs dedicated section of your
> websites.
> This year, we will also include links to the project, which we believe
> would increase its popularity.
>
> It would be great if you'll be able to participate in any way, so
> please, let me know if so
>
> Looking forward to your emails,
> Kind Regards,
> Galia
> |
> |
>
> --
> Galia Mancheva- Project Manager
> Free Software Foundation Europe | www.fsfe.org <http://www.fsfe.org>
> +49-30-27595290 (office)
> +32 488 070 135 (mobile)
> fingerprint: 4195 1315 E14A A00A 0119 6F17 8040 8B16 CADD 6573
> Schönhauser Allee 6/7, 10119 Berlin, Germany
> Registered at Amtsgericht Hamburg, VR 17030
>
> _______________________________________________
> Foss4smes-team mailing list
> Foss4smes-team(a)lists.fsfe.org <mailto:Foss4smes-team@lists.fsfe.org>
> https://lists.fsfe.org/mailman/listinfo/foss4smes-team
>
> This mailing list is covered by the FSFE's Code of Conduct. All
> participants are kindly asked to be excellent to each other:
> https://fsfe.org/about/codeofconduct
>
>
>
> --
>
> turn on images <https://www.tudublin.ie/>
>
>
> Dr. Brian Keegan
>
> Senior Lecturer
>
> City Campus
>
> ________________________________________
>
> www.drbriankeegan.com <http://www.drbriankeegan.com> –
> @tudublincompsci – tudublin.ie <https://tudublin.ie/>
>
> NetAcad self-study: ditcs-netacad
> <https://sites.google.com/mydit.ie/ditcs-netacad>
>
> OT Baile Átha Cliath - Sráid Chaoimhín, D08 NF82, Éire
>
> TU Dublin - Kevin Street, D08 NF82, Ireland
>
>
> <http://www.drbriankeegan.com>
> Academy Support Advisor
> Academy Support Center Staff
>
> *This email originated from TU Dublin. If you received this email in
> error, please delete it from your system. Please note that if you are
> not the named addressee, disclosing, copying, distributing or taking
> any action based on the contents of this email or attachments is
> prohibited. ***
>
> *Is ó OT Baile Átha Cliath a tháinig an ríomhphost seo. Má fuair tú an
> ríomhphost seo trí earráid, scrios de do chóras é le do thoil. Tabhair
> ar aird, mura tú an seolaí ainmnithe, go bhfuil dianchosc ar aon
> nochtadh, aon chóipeáil, aon dáileadh nó ar aon ghníomh a dhéanfar
> bunaithe ar an ábhar atá sa ríomhphost nó sna hiatáin seo.*
>
--
Galia Mancheva- Project Manager
Free Software Foundation Europe | www.fsfe.org
+49-30-27595290 (office)
+32 488 070 135 (mobile)
fingerprint: 4195 1315 E14A A00A 0119 6F17 8040 8B16 CADD 6573
Schönhauser Allee 6/7, 10119 Berlin, Germany
Registered at Amtsgericht Hamburg, VR 17030
Dear FOSS4SMEs partners,
I am contacting you with a communications related proposal.
We, at FSFE,are having an annual campaign taking place on February 14th
each year, where wepromote the use of FOSS.
The way we have done it online so far is by placing the visuals of the
slogan "I love Free Software"
https://fsfe.org/campaigns/ilovefs/artworkeverywhere we can: websites,
blogs, social media platforms (posting,reposting) on February 14th. As
you would notice, the visuals do not include FSFE name, which makes it
easier for other companies and organisations to participate and spread
the message. Some of our volunteers are going to give a 15 minute talk
in front of students with tech profiles on the benefits of using FS on
that day.
In the context of FOSS4SMEs, it makes sense that the project would
promote the day, but we would like to ask if anyone of you would be
willing to participate and share any of those visuals on the online
platforms you are using or on the FOSS4SMEs dedicated section of your
websites.
This year, we will also include links to the project, which we believe
would increase its popularity.
It would be great if you'll be able to participate in any way, so
please, let me know if so
Looking forward to your emails,
Kind Regards,
Galia
|
|
--
Galia Mancheva- Project Manager
Free Software Foundation Europe | www.fsfe.org
+49-30-27595290 (office)
+32 488 070 135 (mobile)
fingerprint: 4195 1315 E14A A00A 0119 6F17 8040 8B16 CADD 6573
Schönhauser Allee 6/7, 10119 Berlin, Germany
Registered at Amtsgericht Hamburg, VR 17030
Dear all,
following our meeting in Dublin I would like to update you on our status.
*Financial information*
We would like to invite FSFE, Dlearn and OFE to send us an invoice of 20%
(for the third payment which is due now) on the FOSS4SMEs project.
We would like to invite DIT to send us an invoice of 80% (for the first,
second and third payment together) on the FOSS4SMEs project.
We would like to invite SKUNI to send us an invoice of 50% (for the second
and third payment together) on the FOSS4SMEs project.
*Timesheets *(scanned as "Certified copies", signed and stamped)
Please send us your timesheets for Oct, Nov and Dec 2018 asap (per person,
per staff category, per output AND Only integer numbers at the sum).
*Travel Documents*
Please send us the following documents for every person for the Dublin trip
(scanned as "Certified copies", signed and stamped)
- Flight itinerary and boarding passes
- Travel invoices, receipts (plane, bus, etc.)
- Subsistence costs invoices/ receipts (hotel, etc.)
*Certificates of participation – Dublin Meet.*
Please scan and upload your certificates as PDF files in the folder -->
K:\team\foss4smes\5. Meetings\3. Dublin Meeting\Certificate of Participation
I checked with our financial department and this is how we need them. The
.jpg files will not do.
*Participants list*
Does OFE have received the list from TUD? ATL would like to have it then
sent to us per post, when everyone has signed.
*Minutes*
I was expecting to receive them by the 25.01. Is it possible to have them
by this Friday? I need to review them and send them around asap.
*Keybase*
As Galia suggested, I have tried to move most of our documents from Google
Drive to Keybase. Please check if there are any documents created by you
left in our Google Drive folder and move them in our Keybase folder. Please
remember to add a date along within the filename e.g. filename_date.xlsx
*O2/A1 1st Peer Review – results for Unit 1*
Please remember that *by Sunday* we should all have updated our units based
on peer review and guidelines from FSFE and OFE. Lets keep fingers crossed
that we will all be able to stick to our strict timeline.
*FOSS tool for Video hosting*
Someone said during the meeting, that there is a FOSS tool for hosting
videos. Which one is that? I need to communicate this to our IT department.
*2nd Newsletter*
Its never too late to send our second newsletter, so please try to prepare
your text asap. You can upload it in the file located -->
K:\team\foss4smes\1. Management\Newsletters
*Test Plan*
Dear Brian, you wanted to send me sth before I start preparing this?
Thank you all in advance for doing a great job! It was so nice spending
time with you in Dublin!
Let me know if you have any questions or difficulties to meet a certain
deadline. We can find a solution.
Best,
Katerina
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>
Hi All,
Thank you all for visiting Dublin last week for what I believe was a
productive meeting. It's always good to catch up in person and to have an
open discussion in a social setting.
I've uploaded the pictures Peter took during the meeting into the Keybase
folder for the Dublin Meeting. You will also find copies of your
certificate of attendance in there.
As a follow-up, we did a short LinkedIn press release for the event
which attracted some attention. The post received over 1000 views in the
first day and has probably peaked now. One interesting insight from the
post was that "Lawyers" were the most popular people who viewed the post.
Regards,
B.
[image: LinkedInPost-FOSS4SMEs.png]
--
Brian Keegan, Ph.D, M.Phil, Pg.Dip (Ed), B.Eng
Senior Lecturer
Programme Chairperson (DT211C, Computer Science - Infrastructure)
School of Computer Science - TU Dublin Kevin Street Campus
web: www.drbriankeegan.com
NetAcad self-study: ditcs-netacad
<https://sites.google.com/mydit.ie/ditcs-netacad>
<http://www.drbriankeegan.com>
Academy Support Advisor
Academy Support Center Staff
--
*This email originated from TU Dublin. If you received this email in
error, please delete it from your system. Please note that if you are not
the named addressee, disclosing, copying, distributing or taking any action
based on the contents of this email or attachments is prohibited. *******
*Is ó OT Baile Átha Cliath a tháinig an ríomhphost seo. Má fuair tú an
ríomhphost seo trí earráid, scrios de do chóras é le do thoil. Tabhair ar
aird, mura tú an seolaí ainmnithe, go bhfuil dianchosc ar aon nochtadh, aon
chóipeáil, aon dáileadh nó ar aon ghníomh a dhéanfar bunaithe ar an ábhar
atá sa ríomhphost nó sna hiatáin seo.*
---------- Forwarded message ---------
From: Brian Keegan <brian.x.keegan(a)dit.ie>
Date: Τετ, 16 Ιαν 2019 στις 3:45 μ.μ.
Subject: Fwd: Your enquiry at The Market Bar (DMN-16708192987)
To: Katerina Tsinari <tsinari(a)abe.gr>, Max Mehl <max.mehl(a)fsfe.org>, <
galia(a)fsfe.org>, Bjorn Lundell <bjorn.lundell(a)his.se>, Jonas Gamalielsson <
jonas.gamalielsson(a)his.se>, Francesco Agresta <francesco.agresta(a)dlearn.eu>,
<sivan(a)openforumeurope.org>, brian. x. keegan <brian.x.keegan(a)dit.ie>,
Brian Gillespie <brian.x.gillespie(a)dit.ie>, Peter Manifold <
Peter.Manifold(a)dit.ie>, Paul Doyle <paul.doyle(a)dit.ie>
Hi All,
We will be meeting for dinner at 7pm this evening in Market Bar (menu
attached).
Market Bar
14A Fade St, Dublin, D02 A368
https://goo.gl/maps/sosz6nN5MpF2
Regards,
B.
---------- Forwarded message ---------
From: The Market Bar <themarketbar(a)partners.collinsbookings.com>
Date: Wed, 16 Jan 2019 at 15:36
Subject: Your enquiry at The Market Bar (DMN-16708192987)
To: Brian Keegan <brian.x.keegan(a)dit.ie>
<http://www.designmynight.com>
* Your enquiry at The Market Bar *
Hi Brian,
As discussed, just email me back to confirm you are happy with the set menu.
Kind Regards,
Tara
------------------------------
*Brian Keegan*
*11 people on Wednesday 16 January 19:00 - 21:00.*
Booking reference: DMN-16708192987
Booking type: Tapas Group (10+people)
[image: #]
Powered by DesignMyNight.com <http://www.designmynight.com/>
[image: #]
--
Brian Keegan, Ph.D, M.Phil, Pg.Dip (Ed), B.Eng
Senior Lecturer
Programme Chairperson (DT211C, Computer Science - Infrastructure)
School of Computer Science - TU Dublin Kevin Street Campus
web: www.drbriankeegan.com
NetAcad self-study: ditcs-netacad
<https://sites.google.com/mydit.ie/ditcs-netacad>
<http://www.drbriankeegan.com>
Academy Support Advisor
Academy Support Center Staff
*This email originated from TU Dublin. If you received this email in error,
please delete it from your system. Please note that if you are not the
named addressee, disclosing, copying, distributing or taking any action
based on the contents of this email or attachments is prohibited. *
*Is ó OT Baile Átha Cliath a tháinig an ríomhphost seo. Má fuair tú an
ríomhphost seo trí earráid, scrios de do chóras é le do thoil. Tabhair ar
aird, mura tú an seolaí ainmnithe, go bhfuil dianchosc ar aon nochtadh, aon
chóipeáil, aon dáileadh nó ar aon ghníomh a dhéanfar bunaithe ar an ábhar
atá sa ríomhphost nó sna hiatáin seo.*
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>
Hi All,
We have fixed the dates for the Dublin Meeting as follows:
Wednesday 16th January 2019
Thursday 17th January 2019
I will assume a maximum of two delegates will be arriving from each
partner. If there are more than two or non-attendance, then please let me
know (I need this for room booking resources).
DIT is currently a multi-location college with locations across the city.
We intend to host the meeting in the Aungier St campus on the first day and
the Grangegorman campus on the second day. Movement to the
Grangegorman campus will depend on the progress we make in the recording
studio on the first day.
Aungier St Camus
https://goo.gl/maps/CTFVM2Ybfn42
Grangegorman Campus
https://goo.gl/maps/1LEtbEaiJrt
There are many hotels in the city center, the closer you get to
St.Stephens Green the more expensive they tend to be. I have indicated
below 3 hotels, keeping in mind the substance and location.
Central Hotel
1- 5 Exchequer Street, D2 Dublin, Ireland
Travelodge Stephens Green
Lower Mercer Street, D02 TW61 Dublin, Ireland
Drury Court Hotel
28-30 Stephen Street Lower, D2 Dublin, Ireland
I will provide more information on meeting room locations as soon as I can.
Looking forward to seeing you all.
Regards,
B
--
Brian Keegan, Ph.D, M.Phil, Pg.Dip (Ed), B.Eng, MIEEE
Senior Lecturer
Programme Chairperson (DT211C, Computer Science - Infrastructure)
DIT School of Computer Science
web: www.drbriankeegan.com
NetAcad self-study: ditcs-netacad
<https://sites.google.com/mydit.ie/ditcs-netacad>
<http://www.drbriankeegan.com>
Academy Support Advisor
Academy Support Center Staff
--
This email originated from DIT. If you received this email in error,
please delete it from your system. Please note that if you are not the
named addressee, disclosing, copying, distributing or taking any action
based on the contents of this email or attachments is prohibited.
www.dit.ie <http://www.dit.ie/>
Is ó ITBÁC
a tháinig an ríomhphost seo. Má
fuair tú an ríomhphost seo trí earráid, scrios
de do chóras é le do thoil.
Tabhair ar aird, mura tú an seolaí ainmnithe, go
bhfuil dianchosc ar aon
nochtadh, aon chóipeáil, aon dáileadh nó ar aon ghníomh
a dhéanfar bunaithe
ar an ábhar atá sa ríomhphost nó sna hiatáin seo. www.dit.ie
<http://www.dit.ie/>
Tá ITBÁC ag aistriú go Gráinseach Ghormáin – DIT is
on the move to Grangegorman <http://www.dit.ie/grangegorman>
Dear all,
I hope you had relaxing and joyful holidays and could manage to take some
time off your desks and working-obligations. I am wishing you in the name
of Atlantis Engineering and my colleagues here, all a happy new year and a
great start in 2019! I am starting 2019 with our main points.
*2nd Payment*
@all, please send us an *invoice (or financing request *for those who can’t
issue an invoice*)*, so that we can settle the second payment of 30% asap.
*Dublin Meeting*
- DIT is now called officially “*Technological University Dublin*” –
Does anything change for us in the project? If yes, DIT will tell us in
Dublin :)
- *17.01. of Dublin Meeting*: @Brian: Since all partners are flying back
in the next day, please consider the option of using our 2nd half of our
2nd day for *re-takes of videos*, enhancing contingency (14.00 – 17.00).
- @DIT please prepare all *supporting documents* for this meeting
including our Certificates of Attendance, the participants list, the
evaluation form, etc.
- @DIT: Please send us *by Friday the final Agenda*, maps for locations,
emergency phone numbers, restaurant info etc.
- *Presentations to be held in Dublin*: @presenters: Please send your
files to me *by 11.01.* (SKUNI on O2/A4, DIT on O2/A1 status, FSFE on
Dissemination and OFE on O3)
- *Guidelines on script-development* for the video recordings: @DIT: are
we going to receive sth from you? If not, we assume you tell us all
about it in Dublin and we all hope that we will have enough time to prepare
ourselves and not be too stressed :)
*Dissemination*
- *2nd Newsletter*: @all: Please insert your text here asap, as we
should have published this in December https
://docs.google.com/document/d/1U_pQ6H5vCYsAF7Ge4WWo9zB1m_XDld2vgsy9p4d81lI/edit
- *Update of Diss. Plan concerning multiplier events with budget cuts*: @
FSFE: This is still open, so please update accordingly.
- *Stakeholders Matrix*: @FSFE: you wanted to send us tips - what
happened?
- *Exploitation Plan (A13):* @FSFE: you wanted to send me an update -
what happened?
- *A8 - Publication of articles*: None of us has published sth relevant.
@FSFE: Can you coordinate this task? @all: Please prepare an article or
a white paper on our research results and project developments so far. I
need one from each of you. In case 2 partners want to work together, it is
possible, but only for just one couple. We need a minimum of 4 articles,
even if they are 1-pagers and a re-writing of our deliverables. They are
targeting a different audience, so be creative!
- *Twitter, Facebook and LinkedIn project page: Our status today is --> *
Facebook: 61 likes, Twitter: 66 followers, Linked In: 11 followers.
@all: Please disseminate the pages and give us at least 20 likes from your
country. @FSFE: Can you coordinate us on the preparation of posts? I
need your support to keep track of this and draft nice texts. Cant make it
alone - Thanks.
- *“Dissemination to-dos” for each partner as a 1-pager: @*FSFE: you
wanted to prepare this for us. Please present it in the Dublin meeting.
- @Galia: ATL is waiting since November for the translation of the *German
Newsletter*. Please upload it here https
://docs.google.com/spreadsheets/d/1-mDxEqX0gWLshzZjpkZaF-1krBx7T3D-Utc31oQhZlo/edit#
gid=1684811769
<https://docs.google.com/spreadsheets/d/1-mDxEqX0gWLshzZjpkZaF-1krBx7T3D-Utc…>
. and tell us when its ready
*Output 2*
- *Units: *our stauts is in Keybase --> FSFE – no deliverable, Dlearn –
finalised, OFE – file not working, DIT – file not working, ATL – update
after DIT review required, SKUNI- finalised. Final is a Unit that
includes pictures, assessment exercises and summaries.
- @ FSFE and OFE: *Peer Review* will happen after solution with FSFEs
delay is found. I still have no news from Max.
- *Translations:* By the beginning of January all training content
should be ready in 5 languages. As soon as our final versions are
available, we are able to start with this next task. Remember to find
translators and check your budget ahead.
- *O2_Training Plan* for the course: @Brian: please remember this task :)
Thank you all in advance.
I am excited to see you next week in Dublin and enjoy 2 fruitful working
days with everyone!
Best,
Katerina
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>
Dear all,
in about 30' we will begin with our last telco before Christmas and our
Dublin Meeting.
The main discussion points for today are:
*- the training plan*
*- the development of the 5 units*
*- the preparation of our 2nd newsletter *
*- the preparation of our Dublin meeting*
You can have a look in the preliminary Agenda for Dublin in our link here:
https://docs.google.com/document/d/1D9PuUDPpiWa99QrrMluix_DD4xYKGGM91yvPDtD…
Our status for the Content Development can be summarised in this table:
O2/A1 Partners 1st submission Update after Review from SKUNI Update after
proofreading from DIT Peer Review by OFE and FSFE Final update from each
partner
ATL - Unit 1 29.11. 13.12.
OFE - Unit 2.1 and 2.2. 03.12. 12.12.
Dlearn - Unti 2.3 and 2.4. 14.09. 14.12. (12:04h) 14.12. (19:14)
Dit - Unit 3 12.12. -
Skovde - Unit 4 30.11. - 17.12.
FSFE - Unit 5
No extra points were sent by you.
I am looking forward to catch up with you shortly and discuss our next
steps towards completion of the "text-part" of our course.
I ll send you the link for our Framatalk room, some minutes before our
meeting.
Best,
Katerina
--
[image: atlantis-logo-for-signatures]
*Katerina Tsinari*
*EU Projects consultant*
*Αntoni Tritsi 21, 570 01 Thessaloniki*
*T:*
*2310 233 266*
*Email:*
*tsinari(a)abe.gr <elsianli(a)abe.gr>*
*URL:*
*www.abe.gr <http://www.abe.gr/>*
*Skype:*
* tsinarikaterina(a)hotmail.de <tsinarikaterina(a)hotmail.de>*
<https://www.linkedin.com/company/atlantis-engineering-sa>
<https://twitter.com/EngAtlantis>
<https://www.facebook.com/Atlantis-Engineering-SA-141993602518655>
<https://plus.google.com/u/0/112248896999799346483>