3rd Newsletter: solution required from FSFE by 11.07.19 (Only OFE, FSFE inserted texts in Keybase folder).
Peer Review of O2/A1 Training Plan: OFE by 12.07.
Feasibility study: by OFE 12.07.
Peer Review FSFE: relevant templates need to be saved in Keybase for both reviewed documents (Training Plan and Platform Design Plan) by 12.07.
Clone of training course: ATL by 12.07
O3/A2 - 01.05.-30.07.19 - Report and consultation: OFE by 16.07.
O3/A2 Peer Review: ATL, Dlearn by 17-31.07.19.
O2/A2 Translation of Training Course contents: all relevant partners by 30.07
O2/A2 Mother tongue videos: Greek ok. rest by 31.07. by Peter/ TUD.
O2/A2 Import of translations in Moodle – finalisation of courses: all relevant partners by 16.08. (Guidelines provided as attachment).
O2/A4: all partners ASAP in their country. Multiplier events. Results of our O2/A4 should be ready before our meeting in Brussels.
TU Dublin Invoice: TUD to reply ASAP. payment still pending.
Certificates of participation – Dublin Meet.: Pending from TUD. ASAP.
Stakeholders Matrix: SKUNI[KT1] , TUD[KT2] should insert 25 entries in the table. ASAP.
O1/A2 executive summary translation: File “FOSS4SMEs_ IO1.A2 Executive Summary”, Translations to be provided by Dlearn, FSFE, and SKUNI in K:\team\foss4smes\2. Implementation\Outputs\Output 1\A2\O1.A2. Summary translations by 01.09.19.
O3/A1 executive summary translation: Dlearn, FSFE, ATL and SKUNI by 01.09.19. in folder K:\team\foss4smes\2. Implementation\Outputs\Output 3\A1\Translated executive summaries
Timesheets 07-09.19: All by 20.9.
Katerina Tsinari | ||
EU Projects consultant | ||
Αntoni Tritsi 21, 570 01 Thessaloniki | ||
T: | 2310 233 266 | |
Email: | ||
URL: | ||
Skype: |