Dear all,
this is an update of our status today and our pending tasks.
*Peer Review FSFE: *relevant templates will be saved in Keybase for both reviewed documents (Training Plan and Platform Design Plan) asap.
*O3/A2 - 01.05.-30.07.19 - Report and consultation: *Peer Review from ATL done. Dlearn pending until 31.07.19.
*O2/A2 Translation of Training Course contents: *all relevant partners by 30.07
*O2/A2 Mother tongue videos*: Greek ok. rest of videos by 31.07. by Peter/ TUD.
*3rd Newsletter: *sent on 26.07.2019.
*Usage scenarios 2 and 3 are ready*: check our page https://www.foss4smes.eu/?page_id=66 to find information.
*Project Website update*: Please go into file “Translations Brochure Website Newsletter” in Keybase and translate the new page marked in yellow by 14.08.19.
*Feasibility study* *by OFE*: Review was sent from Katerina. Updated version is expected by 14.08.19
*O2/A1 Training Plan*: Peer Review completed by OFE and FSFE. TUD to update file by 15.08.
*O2/A2 Import of translations*: all partners by 16.08. (Guidelines provided last time).
*Multiplier events*: Dlearn (and others if applicable) please send us the required supporting documents asap.
*O3 consultation exercise*: to be prepared by OFE and Dlearn in 6-9.09. and saved in K:\team\foss4smes\2. Implementation\Multiplier Events\Multiplier Event 4 – Brussels.
*Timesheets 07-09.19*: All by 20.9.
*O1/A2 executive summary translation: *File “FOSS4SMEs_ IO1.A2 Executive Summary”, Translations to be provided by Dlearn, FSFE, and SKUNI in K:\team\foss4smes\2. Implementation\Outputs\Output 1\A2\O1.A2. Summary translations by 01.09.19.
*O3/A1 executive summary translation: *Dlearn, FSFE, ATL and SKUNI by *01.09.19.* in folder K:\team\foss4smes\2. Implementation\Outputs\Output 3\A1\Translated executive summaries
*O2/A4*: all partners as soon as possible in their country. Multiplier events. Results of our O2/A4 should be ready before our meeting in Brussels.
*4th transnational meeting*: partners can enter travel details here: team/foss4smes/5. Meetings/4. Brussels
*TU Dublin Invoice*: TUD to reply ASAP. payment still pending.
*Certificates of participation – Dublin Meet.:* Pending from TUD. ASAP.
*Stakeholders Matrix*: SKUNI[KT1] <#_msocom_1> , TUD[KT2] <#_msocom_2> should insert 25 entries in the table. ASAP. ------------------------------
[KT1] <#_msoanchor_1>to be able to provide contacts for the stakeholders matrix) we stress the importance of providing content for use under usage scenario 3
[KT2] <#_msoanchor_2>We were working on this in conjunction with our multiplier event so I will get a list from our internal admin
Thank you all for our cooperation. I will be away until 20.08.19, but please feel free to contact me on urgent matters.
Best, Katerina